Milestone risk assessment

Each milestone has a risk assessment tab, which shows the list of items that are potential risks to the completion of the milestone. 

The list includes the following: 

  • Tasks and Bugs without a due date, except those with a status of Completed/Closed/Not a Bug/Deferred/Duplicate
  • Tasks and Bugs without an estimate, except those with a status of Completed/Closed/Not a Bug/Deferred/Duplicate
  • Tasks and Bugs without an assignee, except those with a status of Completed/Closed/Not a Bug/Deferred/Duplicate

The risk factor for each item will be listed under Risk Factors when viewing the list under the Risk Assessment tab. 